Planning Act & consent expiry dates

The Planning Act (PA) and Natural Environment Act (NEA) gained Royal assent on 30 September 2026 and came into force on 31 October 2026. These acts will replace the Resource Management Act 1991 (RMA). However, the RMA continues to apply for a transition period of several years while instruments under the new acts are prepared.

To allow for this transition to the new planning framework, Clause 39 of Schedule 1 of the PA has extended the expiry dates of most RMA consents which would otherwise expire during the transition period. Clause 39 applies to consents with a fixed expiry date, which is most consents granted by regional councils under the RMA. It applies to resource consents that had not yet expired by 30 September 2026 and are due to expire during the transition period and potentially 2-4 years beyond the transition period.

Under the new planning management system these activities will be regulated under the NEA or PA.

Page Header
On this page

What does this mean for existing consents?  

For consents where the extension applies, the existing consent has been automatically deemed to be extended but we currently don’t know the date it will be extended to except that it cannot be earlier than 1 January 2030 unless your consent received a term of 35 years (i.e. your consent was granted in or prior to 1995). 

As a consent holder you can choose to rely on your extended consent until it expires, noting that you: 

  • Can only do the activity covered by the consent. 

  • Will need to continue following the existing consent conditions. 

  • Will continue to receive annual charges for applicable activities. 

  • May need to apply for a new replacement application before the existing consent expires at its extended expiry date (once that date is confirmed in several years) if you wish to continue the activity. The need for replacement consent (which will be then called a permit) under the NEA, or planning consent under the PA, will be determined by National Standards and Natural Environment and Land Use Plans made under that Acts for specific activities. 

  • Can surrender the consent if it is no longer required.   

Once we know the specified transition date (in several years), we will be contacting consent holders whose consents have been automatically extended to let them know their actual extended expiry date. Councils have until three months after the specified transition date to update their records to reflect the automatic extension.   

What if I have a renewal application lodged?  

Existing applications lodged for renewal consents that have already received an extension to 31 December 2027 will receive the PA extension.  

For renewal applications still in progress, which obtained existing use rights and as a result received the previous extension, applicants can decide what to do with their replacement application.  Applicants have the option to withdraw the consent application currently in process to rely on their extended consent, to continue with the processing of it, or to suspend the application (if the criteria for suspension applies).  

Unless you tell us otherwise, we will continue to process your application and standard RMA processing steps still apply. Replacement applications made under the RMA will continue to be processed and decided under the RMA, in the version of the RMA in force at the time the application was lodged (either before or during the transition period). 

If you decide to withdraw an application, we suggest you contact us before taking this action to be clear on what this may mean for you.   

When considering withdrawal of your application it’s important to note that if you do: 

  1. You must continue to operate within the scope of activity authorised by the existing or reinstated consent. Any activities beyond the scope of the existing or reinstated consent will still require a new consent application. 

  2. Compliance with current consent conditions and any outstanding enforcement actions remains mandatory. 

  3. If the replacement application relates to a limited resource (e.g. a water take from a river close to its allocation limit), it may lose any processing priority it may have had based on its lodgment date or application progress. 

  4. Applicants must formally let us know if they wish to withdraw an application. If not, we will continue to process the application until that time. 

  5. The costs of processing the application up to the date an application is withdrawn will be invoiced to you. 

  6. A new replacement application may still be required before the extended consent expires once the expiry date is confirmed (in several years). The need for replacement consent (which will be then called a permit) under the Natural Environment Act will be determined by national standards and Natural Environment Plans made under that Act for specific activities. 

When will I know the actual extended expiry date of my consent?

We won’t know the new expiry date for several years yet. Councils will get at least six weeks’ notice when the specified transition date is set and will be able to determine actual expiries then. Councils have three months after the specified transition date to update their records and we will be working to notify you of your extended expiry date as soon as we can.

From that date, extended consents will have at least 24 months until their expiry which will provide consent holders time to determine whether replacement application is required under the new planning and natural resource system and its rules and regulations developed under the NEA and PA. 

What certainty can I have now?

The minimum extension for qualifying consents is 24 months from the specified transition date.  A clause in the PA says that the specified transition date cannot occur until after 31 December 2027. 

So, if your consent qualifies for extension (i.e. is not related to a municipal, government department or defence force wastewater network and does not exceed 35 years) then your consent will be extended until at least 1 January 2030 or, for water related consents, a maximum of 35 years after the consent commenced, whichever is earlier. Unless your consent is capped at 35 years, this means that while the actual extension may be longer than the start of 2030 when the specified transition date is set, you have at least until the middle of 2029 before a replacement application (if needed) is required to be lodged to be able to carry on your activity while the new application is processed.   

We will be updating our guidance and advice as soon as we can and when we know more about when the specified transition date might be or any regulations made related to consent expiry extensions. 

Will my consent decision document be updated to show it’s been extended?

We can’t update our database or decision documents until we know what the extension dates are and we won’t know that for several years.  The Planning Act requires Councils to update their records within three months after the specified transition date. Affected consent holders will be updated at that time.  As noted above, this is expected to be several years away. 

What if I need to know the details of my consent expiry for business purposes, or for activities related to a property for due diligence?

We suggest providing a copy of the consent with the original or previously extended expiry on it, along with this advice about consent expiries under the PA.  We cannot provide advice on actual expiries until the specified transition date is set. Alternatively, please feel free to get in touch if you need anything further from us.  

Can I apply for a replacement consent early?

You can apply for a replacement consent at any time even if your existing consent is deemed extended.

If the activity you are applying for is the same as for the existing consent you hold you can continue to operate under that consent until your new consent is granted. If you apply for new or expanded activities, you cannot undertake these changes until a new consent is granted but may continue to operate under any existing consent in the meantime. If you apply for consent before the specified transition date you must apply under the RMA requirements. If you apply after the specified transition date you must apply under the PA and NEA requirements including any rules in National Standards and Council plans made under those acts.  

What activities might get further extended up to 48 months after the specified transition date?

We don’t know, and no detail is available until the government makes regulations for this. There is provision for a regulation to be made but it isn’t mandatory. Until or unless there is a regulation for further expiries, we know consents qualifying for extension get extended a minimum of 24 months after the specified transition date. 

How do I know if my activity is “water related”?

The definition requires reference to several sections of the RMA. A general guide is that if your consent is related to any of the following activities it will be “water related”: 

  • A resource consent for taking, using, damming, or diverting of water, heat or energy and does not apply to water in the coastal marine area. Note that some structures in the beds of rivers also dam or divert water and consent provides for both their construction/placement and the action of damming or diverting (e.g. dams, weirs, culverts). 

  • A resource consent for a discharge of contaminant or water into water, or a discharge onto or into land which may result in that contaminant entering water, and includes any contaminant emanating as a result of natural processes from the original contaminant. Does not include discharges to water in the coastal marine area. 

  • A use of land that required resource consent where that use includes associated discharges.  For example, the land use might include disturbances of plants or soil with associated discharges of suspended solids material in the same consent. Because this subclause is restricted to s9 land use consents that include associated discharges, and does not include s13 land use consents, it does not apply generally to structures in the bed of a river (use, erection, reconstruction, placement, alteration, extension, removal or demolition) or the disturbance of the bed of a river, where there is an associated discharge in an individual consent. Note, however, the explanation under part (a) relating to structures that also dam or divert.  If you have a separate discharge consent, part (b) above means that this is automatically ‘water related’. 

If you are not sure if your consent is “water related” or not and it was granted in 1999 or earlier, we encourage you to get advice or contact us to confirm. 

Will I still be charged annual charges for my consent?

Yes, if your consent currently attracts annual charges, these will continue for the duration of the consent. 

What if I don’t need my consent anymore?

Your consent is extended automatically if the activity qualifies for an extension. The legislation means the extension will automatically apply even if you no longer need your consent. You can surrender your consent at any time if you don’t intend to carry out or continue the activity, or it was a short term or temporary activity, and you no longer need the consent. We recommend you talk to us before surrendering your consent as we can’t just reinstate it if you change your mind.

Still have questions?  

We encourage you to contact us if you are not sure if the consent duration extension applies to your specific consent, or what the implications are for that consent or an associated application. We particularly suggest you do this before considering withdrawing any application that is currently in progress.   

For in-progress replacement applications you should contact the Horizons staff member processing your application in the first instance. For general enquiries about other consents, these can be sent to: consents.enquiries@horizons.govt.nz or call 0508 800 800.